Civil Construction
At Sarjaro, we specialize in delivering high-quality civil construction work, ensuring that every project is executed with precision, safety, and sustainability in mind.


The Southport School (TSS) Tennis Court Development
Sarjaro were engaged by TSS to design, construct and project manage the upgrade to the senior school tennis court precinct and carpark redevelopment. The works included the build of 5 tennis courts, inclusive of:
- Demolition and offsite disposal of existing chain-link fence
- Excavation, crushing and disposal of 3,000m2 of asphalt/concrete surfaces
- Cut and fill to reuse existing subgrade material and ensure it is geotechnically suitable
- Import and compact new subgrade material
- Supply and install 3000m2 geosynthetic liner
- Supply and install 30mm bedding layer of crusher dust over existing subgrade
- Construct and grade 3,000m2 of new 100mm thick concrete including all reinforcing steel
- Demolish existing 80mx 1m retaining wall
- Installation of new drainage pipe, root barriers lining and stormwater pits
- Construct new 80m x 1m high block retaining wall
- Construct new block hit up wall 10m x 3m high
- Supply and install new posts, nets, and furniture for all five courts
- Supply and install 300m new 3.6-metre-high perimeter fencing and court divider fencing
- Supply and install 20 LED lights on 12 new poles including all electricals
- Supply and install new acrylic surfaces and line marking to new courts
- Demolition and offsite disposal of existing chain-link fence
- Excavation, crushing and disposal of 3,000m2 of asphalt/concrete surfaces
- Cut and fill to reuse existing subgrade material and ensure it is geotechnically suitable
- Import and compact new subgrade material
- Supply and install 3000m2 geosynthetic liner
- Supply and install 30mm bedding layer of crusher dust over existing subgrade
- Construct and grade 3,000m2 of new 100mm thick concrete including all reinforcing steel
- Demolish existing 80mx 1m retaining wall
- Installation of new drainage pipe, root barriers lining and stormwater pits
- Construct new 80m x 1m high block retaining wall
- Construct new block hit up wall 10m x 3m high
- Supply and install new posts, nets, and furniture for all five courts
- Supply and install 300m new 3.6-metre-high perimeter fencing and court divider fencing
- Supply and install 20 LED lights on 12 new poles including all electricals
- Supply and install new acrylic surfaces and line marking to new courts


Scenic Rim Regional Council
Sarjaro was engaged by Scenic Rim Regional Council to remove silt from two ponds at the Tamborine Mountain Botanic Gardens. Sarjaro undertook the comprehensive pond remediation project during the winter season and the works involved the following:
• Site Establishment - Temporary fencing, signage, equipment delivery, and erosion control.
• Pond Remediation - Included bypassing the 70 litres per second water flow of the stream using four large pumps (24 hours an day for the duration of the project), excavation dewatering, constant sediment drying, and phased excavation.
• The Excavation works included excavating wet sediment and stockpiling approximately 1,000m³ of silt near the rock bridge.
• Soil remediation included the Blending lime / sawdust and fly ash into the silt for stabilization using an excavator with a sieve bucket.
• Loading, Transporting and disposal works followed the treatment works and care was required to move material from the top of the mountain down to the bottom for disposal at JGI Quarry and Recycling in Oxenford.
• Environmental & Safety Measures: Ongoing water quality testing, fauna assessment, and relocation took place with spotter catcher during the works.
• Structural Works: were also ongoing and this included Installing culvert plugs, inspecting pond conditions, and implementing temporary access solutions throughout the project.
This project ensured environmental compliance and site stability for future use, while enhancing the environmental health and aesthetics of the Botanic Gardens for the local community to enjoy for future generations.
• Site Establishment - Temporary fencing, signage, equipment delivery, and erosion control.
• Pond Remediation - Included bypassing the 70 litres per second water flow of the stream using four large pumps (24 hours an day for the duration of the project), excavation dewatering, constant sediment drying, and phased excavation.
• The Excavation works included excavating wet sediment and stockpiling approximately 1,000m³ of silt near the rock bridge.
• Soil remediation included the Blending lime / sawdust and fly ash into the silt for stabilization using an excavator with a sieve bucket.
• Loading, Transporting and disposal works followed the treatment works and care was required to move material from the top of the mountain down to the bottom for disposal at JGI Quarry and Recycling in Oxenford.
• Environmental & Safety Measures: Ongoing water quality testing, fauna assessment, and relocation took place with spotter catcher during the works.
• Structural Works: were also ongoing and this included Installing culvert plugs, inspecting pond conditions, and implementing temporary access solutions throughout the project.
This project ensured environmental compliance and site stability for future use, while enhancing the environmental health and aesthetics of the Botanic Gardens for the local community to enjoy for future generations.


Blanches Bus Depot UST Removal & AST Installation
Underground Petroleum Storage System (UPSS) Remediation, followed by the additional relocation, installation, and commissioning of an Aboveground Storage Tank (AST) at Blanch’s Bus Depot in Ballina.
Sarjaro was engaged by CDC and Tim Fitzroy & Associates to remove one (1) underground storage tanks (USTs) from an operating bus depot in Ballina, NSW. Following the UST removal works, Sarjaro were contracted to relocate, install, and commission an Aboveground Storage Tank (AST) in the same location.
This project includes:
• Removal of one (1) 17,000 litre UST, associated product lines, fuel bowser, fill points, and large concrete tank anchors.
• Compliance with NSW UPSS Regulation and SafeWork NSW for UST decommissioning.
• Eliminating petroleum hydrocarbon sources and backfilling tank voids with clean, locally sourced VENM material.
• Advancing site remediation to align with potential residential zoning under NEPC guidelines.
• Concrete Reinstating - installing an AST raft slab per engineering specifications.
• Reconnecting switchboard and bus wash electrical systems, identifying underground cabling, trenching, and commissioning.
• Reinstating recycled water connections and installing new copper piping.
• Installing a concrete apron, relocating industrial outlets, and demolishing/removing of workers site sheds and recycled water taps.
• Inspecting and ensuring compliance of the AST before transport.
• Transporting the AST from Byron Bay to Ballina, including cranage and site preparation.
• Modifying the fuel container for optimal functionality, including ladder relocation, dispenser upgrades, filtration system installation, and integration of a Smartfill Fuel Management System.
• Installing environmental controls, underground service location, and necessary fire safety measures.
• Ensuring compliance with AS 1940-2017, NSW EPA, SafeWork NSW, and other relevant regulations.
• Commissioning the AST with calibration, staff training, and regulatory certification.
This project contributed to environmental restoration and regulatory compliance for future land use, while ensuring the upgrade enhances fuel storage safety, efficiency, and compliance at the Ballina depot for years to come.
Sarjaro was engaged by CDC and Tim Fitzroy & Associates to remove one (1) underground storage tanks (USTs) from an operating bus depot in Ballina, NSW. Following the UST removal works, Sarjaro were contracted to relocate, install, and commission an Aboveground Storage Tank (AST) in the same location.
This project includes:
• Removal of one (1) 17,000 litre UST, associated product lines, fuel bowser, fill points, and large concrete tank anchors.
• Compliance with NSW UPSS Regulation and SafeWork NSW for UST decommissioning.
• Eliminating petroleum hydrocarbon sources and backfilling tank voids with clean, locally sourced VENM material.
• Advancing site remediation to align with potential residential zoning under NEPC guidelines.
• Concrete Reinstating - installing an AST raft slab per engineering specifications.
• Reconnecting switchboard and bus wash electrical systems, identifying underground cabling, trenching, and commissioning.
• Reinstating recycled water connections and installing new copper piping.
• Installing a concrete apron, relocating industrial outlets, and demolishing/removing of workers site sheds and recycled water taps.
• Inspecting and ensuring compliance of the AST before transport.
• Transporting the AST from Byron Bay to Ballina, including cranage and site preparation.
• Modifying the fuel container for optimal functionality, including ladder relocation, dispenser upgrades, filtration system installation, and integration of a Smartfill Fuel Management System.
• Installing environmental controls, underground service location, and necessary fire safety measures.
• Ensuring compliance with AS 1940-2017, NSW EPA, SafeWork NSW, and other relevant regulations.
• Commissioning the AST with calibration, staff training, and regulatory certification.
This project contributed to environmental restoration and regulatory compliance for future land use, while ensuring the upgrade enhances fuel storage safety, efficiency, and compliance at the Ballina depot for years to come.


Logan City Netball Precinct Redevelopment
Sarjaro were engaged by Logan City Netball Association (LCNA) to demolish and reconstruct 6 asphalt netball courts for the growing community surrounding Ewing Park. The works were completed over two stages and included:
- Excavation and disposal of 1100m3 of existing asphalt and subgrade
- Import and compaction of 1300m3 subgrade and subbase
- Import and spreading of 200m3 crusher dust bedding
- Supply and install 4500m2 Mirafi Geosynthetic liner
- Supply and install 1000LM Megaflow 170 subgrade drainage pipe
- Supply and lay 4,500m2 asphalt
- Supply and lay acrylic surface paint 4000L
- Supply and install new goal posts and footings
- Excavation and disposal of 1100m3 of existing asphalt and subgrade
- Import and compaction of 1300m3 subgrade and subbase
- Import and spreading of 200m3 crusher dust bedding
- Supply and install 4500m2 Mirafi Geosynthetic liner
- Supply and install 1000LM Megaflow 170 subgrade drainage pipe
- Supply and lay 4,500m2 asphalt
- Supply and lay acrylic surface paint 4000L
- Supply and install new goal posts and footings